Difference between revisions of "Chris-201204"

From Stadm
Jump to navigationJump to search
 
(5 intermediate revisions by the same user not shown)
Line 4: Line 4:
 
<div style='display: none;'> BEGIN PARSING ENTRIES - DO NOT REMOVE THIS LINE</div>
 
<div style='display: none;'> BEGIN PARSING ENTRIES - DO NOT REMOVE THIS LINE</div>
 
==Week of 2012-04-28 to 2012-04-30==
 
==Week of 2012-04-28 to 2012-04-30==
<!------------------------------- BEGIN COMMENTED WEEKLY SECTION ---------------------------------
+
 
===2012-04-30 Mon -- 0 hrs===
+
===2012-04-30 Mon -- 2 hrs===
 +
*eri: 1.5h: looked over old rack layout project and fpdf capabilities
 +
*eri: 30m: labeled a few more cables, updated firewall section of cisn display instructions
  
 
<font color='blue'>
 
<font color='blue'>
Line 15: Line 17:
  
 
</font>
 
</font>
-----------------------------------END COMMENTED WEEKLY SECTION ----------------------->
+
 
 
==Week of 2012-04-21 to 2012-04-27==
 
==Week of 2012-04-21 to 2012-04-27==
  
===2012-04-27 Fri -- 0 hrs===
+
===2012-04-27 Fri -- 3 hrs===
 +
*eri: 1.5h: labeled network cables
 +
*eri: 1.5h: working with FPDF and rack description layout
  
 
===2012-04-26 Thu -- 0 hrs===
 
===2012-04-26 Thu -- 0 hrs===
Line 24: Line 28:
 
===2012-04-25 Wed -- 0 hrs===
 
===2012-04-25 Wed -- 0 hrs===
  
===2012-04-24 Tue -- 0 hrs===
+
===2012-04-24 Tue -- 3 hrs===
 +
*eri: 2h: went with Aaron to Webb to fix cisn display
 +
*eri: 1h: learning php stuff for rack desc. project
  
 
===2012-04-23 Mon -- 2 hrs===
 
===2012-04-23 Mon -- 2 hrs===
 +
*eri: 2h: got introduced to rack description php project
  
 
<font color='blue'>
 
<font color='blue'>

Latest revision as of 12:54, 30 April 2012

Daily Entries

BEGIN PARSING ENTRIES - DO NOT REMOVE THIS LINE

Week of 2012-04-28 to 2012-04-30

2012-04-30 Mon -- 2 hrs

  • eri: 1.5h: looked over old rack layout project and fpdf capabilities
  • eri: 30m: labeled a few more cables, updated firewall section of cisn display instructions

2012-04-29 Sun -- 0 hrs

2012-04-28 Sat -- 0 hrs

Week of 2012-04-21 to 2012-04-27

2012-04-27 Fri -- 3 hrs

  • eri: 1.5h: labeled network cables
  • eri: 1.5h: working with FPDF and rack description layout

2012-04-26 Thu -- 0 hrs

2012-04-25 Wed -- 0 hrs

2012-04-24 Tue -- 3 hrs

  • eri: 2h: went with Aaron to Webb to fix cisn display
  • eri: 1h: learning php stuff for rack desc. project

2012-04-23 Mon -- 2 hrs

  • eri: 2h: got introduced to rack description php project

2012-04-22 Sun -- 0 hrs

2012-04-21 Sat -- 0 hrs

Week of 2012-04-14 to 2012-04-20

2012-04-20 Fri -- 0 hrs

2012-04-19 Thu -- 0 hrs

2012-04-18 Wed -- 0 hrs

2012-04-17 Tue -- 1.5 hrs

  • eri: 1.5h: studied drupal concepts, worked on annual report drupal stuff

2012-04-16 Mon -- 4.5 hrs

  • eri: 30m: reassembled Dunkirque(dead power supply)
  • eri: 30m: moved junk from 6706 to 1st floor
  • eri: 1h: brought CISN display to geol dept. and set it up with Aaron
  • eri: 45m: getting back into drupal stuff

2012-04-15 Sun -- 0 hrs

2012-04-14 Sat -- 0 hrs

Week of 2012-04-07 to 2012-04-13

2012-04-13 Fri -- 0 hrs

2012-04-12 Thu -- 0 hrs

2012-04-11 Wed -- 0 hrs

2012-04-10 Tue -- 0 hrs

2012-04-09 Mon -- 3.5 hrs

  • eri: 2h: removed batteries from UPS frames and prepared them for EHS pickup, put new batteries in frame for UPS 1000 for testing
  • geol: 1h: worked out kinks in CISN display, can now remote login to cisndisplay account through ssh

2012-04-08 Sun -- 0 hrs

2012-04-07 Sat -- 0 hrs

Week of 2012-04-01 to 2012-04-06

2012-04-06 Fri -- 0 hrs

2012-04-05 Thu -- 0 hrs

2012-04-04 Wed -- 0 hrs

2012-04-03 Tue -- 2 hrs

  • eri: 2h: finished update of CISN Display installation instructions

2012-04-02 Mon -- 4 hrs

  • geol: 3.5h: finished installing CISN Display
  • eri: 30m: updating old CISN Display installation instructions

2012-04-01 Sun -- 0 hrs

FINISH PARSING ENTRIES - DO NOT REMOVE THIS LINE

Recharge Examples/Entry Instructions


Recharge Entry Examples (each entry is expected to follow a list tag entry in the final html (ie: an asterisk in the wiki editor)):
NEES:20 min:Backups
Frew:20:Backups -- implied units -- units default to minutes
Dozier:1.5h:Backups -- units flexible - space between amt and units optional, h is shorthand for hours, m shorthand for minutes
Davey/Frew/Dozier:20 min each:Backups -- create recharge entries for this amt of time for each of the categories
Davey/Frew/Dozier:2 hours split:Backups and Desktop support -- split time equally between each of the categories

Project examples: - ie: NEES, Snow, Oceancolor, Dragon, CCBER

More detailed Syntax:
ENTRY = ACCT[[/ACCT]...]:AMT [UNIT [LOOP-OP]]:[DESC] -- one entry per line
ACCT = PI | Project | Account | Category -- PI/Project/Acct/Category : ie: Frew, NEES, Dragon, Infra, conf,...
AMT = float | integer -- Amount of time spent -- float or int
UNIT = [hour|hr|h|minute|min|m] -- units of time to apply to amount - default is minute -- spaces optional between amt and units
LOOP-OP = [each|split] -- specialized operators - CATEGORY list is split on "/"s and an entry created for each one when processed.

Non-direct Recharge entries:
*admin - efforts for administrative staff
-
*lic.[itt, matlab, math, arcgis] licensing stuff.
*web.[drupal,wiki,cms,ftp]
-
*stor.[disk,bk,tape]
**bk - efforts relating to backups
**disk - disk server related time
**tape - tape backups
-
*eri.[ ,net,dev,team,ucsb,stadm,dsr]
**eri - alone infers ERI business (infra/sysadm/blahblahblah).
**net - efforts relating to departmental networking (cabling,
**dev - software development, scripting, new services...
**team - efforts relating to IT team meetings/discussions... how about powow?
**ucsb - UCSB training/meetings/discussions/committees or campus greater good.
**stadm - efforts relating to any IT student assistants
**dsr - efforts relating to departmental safety representative work

Other Stuff

AVWH: 168